Ajman’s 2026 Structural Submission Rules: The Unifier Checklist, Third-Party Review and Soil Report

The Unifier deliverables checklist, third-party review, soil report and pile checks, from the structural sets of our 2026 buildings.

Have a question? Message us on WhatsApp
By Sarmed Tariq • Updated November 19, 2026 • 9 min read

In April 2026, the structural engineer on our Al Nuaimia building signed a seven-page form. It was prepared to go to Ajman Municipality with the structural drawings, through the municipality’s Unifier system.

Every line on that form had three boxes: compliant, not applicable, or a reason for not complying. The form itself warns that an incomplete one will be rejected.

Here is the short answer on Ajman structural approval in 2026. The consultant submits a Design Deliverables Compliance Checklist through Unifier, at the same time as the structural drawings. It covers the design report, the drawings and a detailed design review. It adds a third-party structural review where the municipality mandates one. It also covers the soil report and piled foundations.

In this guide, you will find:

  • What the checklist asks for, section by section.
  • When a third-party structural review applies.
  • What the soil report and piled foundations must show.
  • What the rules mean for you as an owner, and for your contractor.

Everything below comes from the checklists and structural notes in our own 2026 drawing sets, with names removed. We have worked as a building construction company in Ajman since 2017.

What Is the Ajman Structural Approval Checklist?

It is a municipality form that the consultant fills in for every structural submission. The form calls itself a prerequisite to all design submissions, for consultant use only. It goes in through Unifier with the drawings. Each item is marked compliant, not applicable, or given a reason.

It is really several checklists in one. They cover the design report and drawings, the soil report, the detailed design and piled foundations. The form opens with five guidelines. Submit on time, as per the approved programme. Keep the quality to the municipality’s standard. Coordinate every discipline, with no discrepancies. Follow current codes and authority rules. And complete the checklist in full.

That last line has teeth. If any check point is incomplete, or a non-compliance is not justified, the submission will be rejected.

Two of our three 2026 structural sets carry this form. They are for our buildings in Al Nuaimia and on piles in Al Jurf. Our guide to the building permit for a residential building shows where structural approval sits. For the wider process, see our guide to construction approvals in Ajman.

Ajman structural approval: diagram of the five parts of the Ajman structural deliverables checklist, from the design report to piled foundation checks

What Must the Design Report Include?

Seven items. The structural model, in 3D and 2D, and the design calculations. Details of any special conditions, such as large spans or cantilevers. The final soil investigation report and the foundation calculations. A wind tunnel report and a PT specialist’s letter, where they apply.

  1. Structural model, with 3D and 2D software models issued
  2. Details of special conditions: large spans, trusses, cantilevers
  3. Structural design calculations
  4. Final soil investigation report
  5. Foundation calculations: bearing pressure and settlement
  6. Wind tunnel report, if applicable
  7. Letter from a post-tension specialist confirming the slab thicknesses, if applicable

Note the word “final” on the soil report. The structural design rests on it, so it must be ready before the structural drawings go in. Our 11-level residential and commercial tower in Al Jurf used post-tensioned slabs.

Which Drawings Must Go In With the Checklist?

The checklist lists 18 drawing items. They run from the general notes and foundation plans to every slab, column, wall and stair. Design loads must be shown for each floor. The last item is the designer’s registration card and signature, with the consultant’s stamp.

  • Foundations: foundation plans with footings, piles, beams, pits and ramps, plus the pile layout and schedule.
  • Floors: framing plans with slab thickness, slab type (RC, PT or hollow-core), top and bottom reinforcement, and all openings.
  • Vertical elements: the column layout with design loads, and schedules for columns, walls and beams.
  • Details: expansion joints, reinforcement drawings, staircases and ramps, the water tank, excavation and any steel or pool.
  • Readability: all drawings to scale and readable in PDF.

A full set helps the contractor too. Clear slab types, loads and reinforcement on paper mean fewer questions on site.

What Is the Third-Party Structural Review?

It is an independent review of the structural design. The checklist describes it as reviewing, auditing and approving the plans, calculations, documents and test results. It also covers monitoring and inspecting the project. It applies to all projects the municipality mandates. On both of our 2026 checklists, it was marked not applicable.

The form does not say which projects are mandated. Ask your consultant early whether yours is.

Tall buildings have a separate rule on the permit checklist. Buildings of 19 floors and above need a letter, licence and certificate from an advisory checker. The piled foundation checklist also asks for any peer review or third-party check to be attached, if required.

What Does the Soil Report Checklist Ask For?

A full picture of the ground. That means boreholes, soil layers and properties, groundwater and clear foundation advice. It needs at least 3 boreholes for each 900 m². It also checks pile capacities where piles are used and liquefaction potential. The seismic classification is for zone 2B under UBC 1997.

  • Exploration: borehole locations, depth, sampling methods, voids and aggressive ground.
  • Soil properties: grain size, compaction, shear strength, bearing capacity and subgrade modulus.
  • Piles: capacities in compression and tension, and single pile settlement.
  • Groundwater: depth to the water table and seasonal changes.
  • Recommendations: foundation type and depth, ground improvement, excavation and dewatering, and settlement.

The permit checklist also asks for the soil report to come from an accredited laboratory in Ajman. Our guide to pile or raft foundation cost shows how the report decides the foundation.

Related guide: Soil investigation for buildings in Ajman

What Extra Checks Apply to Piled Foundations?

A separate checklist for piled rafts and pile caps. It covers raft thickness, punching shear, pile-to-raft details, settlement and the analysis model. Our piled building’s drawings added the site tests. Two working piles per diameter get load tests, and every pile gets an integrity test.

The piled checklist asks for detailed modelling. The raft mesh must be no larger than 0.5 m. Punching at pile caps is checked separately, particularly at corner piles. That applies to basement and seismic buildings. Settlement must meet the authority’s limits.

The site tests come from the structural notes of our piled Ground + 6 in Al Jurf. Load tests go up to 1.5 times the pile capacity. The same notes call for concrete designed for sulphate exposure, epoxy-coated steel and a membrane on the pile caps.

Check that your contractor’s quote says whether those tests are included. Our civil works service covers the piling and foundation stage. Our building construction cost breakdown shows what foundations cost.

Card showing pile load tests on two working piles per diameter up to 1.5 times capacity, and integrity tests on every pile

Which Codes and Loads Does the Checklist Expect?

The checklist names ACI 318 and the UAE code for design. Load combinations follow UBC 97 or ASCE 7-22. It asks for appropriate software, with ETABS, SAFE, SAP2000 and STAAD as examples. It also checks deflection, crack width, fire resistance and coordination with the other drawings.

Coordination gets its own section. Columns, walls and openings must match across the structural, architectural and MEP drawings. Slab names must follow the architectural drawings. The drawings must also match the calculations.

Durability counts too. The checklist asks about concrete grade, cover and corrosion protection. Our guide to civil work standards in Ajman covers what that looks like on site.

What Do These Rules Mean for Owners and Contractors?

For owners, they mean a full file before structural approval, but fewer surprises later. Get the final soil report early, and budget time for the checklist. For contractors, a complete structural set means clear loads, slab types and tests before work starts.

The structural notes also put duties on the contractor. Our Al Nuaimia set says the contractor shall test the concrete and steel when the consultant asks. That testing comes at no extra cost. Our guide to quality civil work in Ajman covers how we check it on site.

Your consultant fills in the checklist and submits it. Your contractor builds to the approved drawings. Our guide to the engineering consultant and building contractor explains who does what. Our approvals and permits service follows the file with your consultant.

Five-step flow from soil report and design to the Unifier submission, municipality review and approval

Frequently Asked Questions

What is Unifier in Ajman?

It is the system the municipality uses for design submissions. The structural checklist must be submitted through Unifier with the drawings, at the same time.

Who fills in the structural checklist?

The consultant. The form says it is for consultant use only. The designer signs it, with the consultant’s stamp. On our Al Nuaimia set, that was the structural engineer.

What happens if the checklist is incomplete?

The form says the submission will be rejected. That applies to any check point left incomplete, or any non-compliance without a reason.

Does every building need a third-party structural review?

No. It applies to projects the municipality mandates. Both of our 2026 checklists marked it not applicable. Ask your consultant about your project.

How many boreholes does the soil report need?

At least 3 for each 900 m², according to the soil report checklist in our 2026 sets.

Which seismic zone does Ajman use?

The soil report checklist asks for the seismic site classification for zone 2B, under UBC 1997.

When is a PT specialist letter needed?

When the slabs are post-tensioned. The checklist asks for a letter from a PT specialist confirming the slab thicknesses.

What pile tests do our drawings require?

Our piled building’s notes call for load tests on two working piles per diameter, up to 1.5 times capacity. Every pile also gets an integrity test.

Does the soil report need to be final before structural submission?

Yes. The design report section asks for the final soil investigation report, and the foundation calculations rely on it.

Can you help with the structural submission?

We work with your consultant on the file and build to the approved drawings. Use our contact page or WhatsApp to talk to us.

So, What Does Structural Approval in Ajman Take Now?

A complete file. The structural drawings, the calculations, the final soil report and the deliverables checklist go in together through Unifier. Piled foundations need their own checks. Some projects also need a third-party review.

Remember the seven-page form from Al Nuaimia. Every line was ticked or explained before the drawings went in. That is what the checklist for Ajman Municipality structural approval asks of the consultant.

Planning a building? See our residential building construction and commercial building construction services. Permit services are listed on the Ajman Municipality e-services portal.

Has your consultant mentioned the Unifier checklist yet? Send us your questions on WhatsApp, and we will walk you through what it means for your building.

Build with confidence

Ready to start your project in Ajman?

From Ajman Municipality approvals to handover, our licensed team manages every step. Share your plot and plans and we’ll give you a clear estimate.

Get in touch

Let’s talk about your project

Visit our office in Al Alia, call or WhatsApp us, or send your plot details, and our team will get back to you with clear next steps.

Request a free consultation

Tell us about your plot and project. No obligation – we’ll reply with a clear estimate.

Thank you! Your request has been sent. Our team will get back to you shortly.

Licensed contractor since 2017

Permits coordinated with your consultant

Villas, residential and commercial buildings

Contact details

+971 55 509 0396

info@sarmedcontracting.com

Al Raeesi Building - Shop 9 - Al Alia - Ajman

Free consultation

Book a Free Consultation

Tell us about your plot and what you want to build. Our engineers will call you back with a clear next step.

Thank you! Your request has been sent. Our team will get back to you shortly.

Prefer to talk? Call +971 55 509 0396 or WhatsApp us